| How to set the next week start date | How to set the next week start date 2007-04-27 - By Rebhan, Gilbert
to quick ;-)
corrected <project name="bla" default="main" basedir=".">
<target name="depends">
<script language="ruby"> <![CDATA[
t = Time.now puts t.strftime("actual date == %m.%d.%Y") x=t.strftime("%w").to_i-1
thisweek = (t - x * 86400).strftime("%m.%d.%Y") $project.setProperty "thisweek", thisweek
lastweek = (t - x * 86400 - 7 * 86400).strftime("%m.%d.%Y") $project.setProperty "lastweek", lastweek
nextweek = (t - x * 86400 + 7 * 86400).strftime("%m.%d.%Y") $project.setProperty "nextweek", nextweek ]]> </script>
</target>
<target name="main" depends="depends">
<echo> starting Date last week == ${lastweek} starting Date this week == ${thisweek} starting Date next week == ${nextweek} </echo>
</target> </project>
Buildfile: C:\WKS\eclipse_3_2_2\test\jruby_time.xml depends: [script] actual date == 04.27.2007 main: [echo] starting Date last week == 04.16.2007 [echo] starting Date this week == 04.23.2007 [echo] starting Date next week == 04.30.2007 BUILD SUCCESSFUL Total time: 2 seconds
Regards, Gilbert
-----Original Message----- From: Rebhan, Gilbert Sent: Friday, April 27, 2007 1:39 PM To: 'Ant Users List' Subject: RE: How to set the next week start date
Hi,
quick hack
--------------------------------------------------------------------- To unsubscribe, e-mail: user-unsubscribe@(protected) For additional commands, e-mail: user-help@(protected)
|
|
 |